西南石油大学学报(自然科学版) ›› 2013, Vol. 35 ›› Issue (2): 164-169.

• 石油机械工程及其他 • 上一篇    下一篇

桥塞坐封过程仿真模拟研究

何祖清1,丁士东1,练章华2,彭汉修1,林铁军2   

  1. 1. 中国石化石油工程技术研究院,北京朝阳1001012.“油气藏地质及开发工程”国家重点实验室 西南石油大学,四川成都610500
  • 收稿日期:1900-01-01 修回日期:1900-01-01 出版日期:2013-04-01 发布日期:2013-04-01

Setting Process Simulation on Bridge Plug Research

He Zuqing1, Ding Shidong1, Lian Zhanghua2, Peng Hanxiu1, Lin Tiejun2   

  1. 1. Research Institute of Petroleum Engineering Technology,SINOPEC,Chaoyang,Beijing 100101,China2. State Key Laboratory of Oil and Gas Reservoir Geology and Exploitation,Southwest Petroleum University,Chengdu,Sichuan 610500,China
  • Received:1900-01-01 Revised:1900-01-01 Online:2013-04-01 Published:2013-04-01

摘要: 桥塞作为井下封层技术的关键设备,由于它施工工序少、周期短、卡封位置准确而得到了广泛应用。针对设
计的可钻式非金属桥塞坐封过程开展模拟研究,涉及弹塑性材料接触、超弹性材料接触和非金属材料动态断裂的非线
性动力学问题,利用有限元法建立该桥塞全尺寸模型和所有部件之间的广义接触关系,通过有限元模拟动态坐封过程
获得桥塞各部件运动变形特性、桥塞与套管之间的密封特性和动态坐封力等数据,该桥塞坐封完成时,坐封机构部件
轴向位移110 mm,坐封力约45 kN。模拟坐封也为进一步优化该型桥塞的结构和评估坐封性能提供了理论依据,对该
型桥塞的推广应用奠定了基础。

关键词: 桥塞, 坐封过程, 密封, 有限元, 动力学

Abstract: The bridge plug is the key equipment of downhole sealing layer technology,which is widely used because of the
advantages of less construction process,short period,and accurate sealing position. The setting process of A-type drillable nonmetallic
bridge plug was simulated which involvs the general contact of elastic-plastic material,the nonlinear dynamics of the
super-elastic material contact and non-metallic materials,dynamic fracture. With the finite element method,we establish the
generalized contact relationship between the full-size model of the bridge plug and all the parts. The finite element simulation
result includes dynamic movement and deformation characteristics of various components of the bridge plug,bridge plug and
the casing between the sealing characteristics and dynamic setting closure force data. The setting axial displacement of the
bridge plug was 110 mm and setting force near 45 kN. The result was also a theoretical basis for further optimization of the
structure and assessment of the bridge plug and setting performance for application in oilfield.

Key words: bridge plug, setting process, seal, finite element, dynamics