西南石油大学学报(自然科学版) ›› 2013, Vol. 35 ›› Issue (1): 116-121.

• 石油与天然气工程 • 上一篇    下一篇

高含水期点坝水平井挖潜适应性界限研究

李俊键1,刘玉章1,肖康2,姜汉桥2   

  1. 1. 中国石油勘探开发研究院采油工程研究所,北京海淀1000832. 中国石油大学石油工程教育部重点实验室,北京昌平102249
  • 收稿日期:1900-01-01 修回日期:1900-01-01 出版日期:2013-02-01 发布日期:2013-02-01

Study on the Adaptability Limits of Point Bar Potential Tapping byHorizontal Well at High Water Cut Stage

Li Junjian1, Liu Yuzhang1, Xiao Kang2, Jiang Hanqiao2   

  1. 1. Research Institute of Petroleum Exploration & Development(RIPED),PetroChina Company Limited,Haidian,Beijing 100083,China2. MOE Key Lab of Petroleum Engineering,China Petroleum University,Changping,Beijing 102249,China
  • Received:1900-01-01 Revised:1900-01-01 Online:2013-02-01 Published:2013-02-01

摘要: 利用孤岛油田Ng4 砂组地质及动态数据,对点坝内部侧积夹层进行定量化描述,建立了一系列反映点坝内部
构型的三维典型精细地质模型,结合水平井经济极限产量,以不同注采条件下的点坝剩余油分布模式为基础,应用油
藏工程以及数值模拟方法,对高含水期点坝水平井挖潜适应性界限进行了研究。研究结果表明,顺侧积夹层注水开发
时,侧积夹层渗透率小于12 mD、倾角小于7°、延伸比例大于0.46、间距小于60 m 时,适合水平井部署水平井挖潜;逆
侧积夹层注水开发时,侧积夹层渗透率小于30 mD、倾角小于11°、延伸比例大于0.33、间距小于90 m 时,适合水平井
进行挖潜。这将为高含水期点坝储层中水平井部署提供一定的理论指导。

关键词: 高含水期, 点坝, 水平井, 适应性界限

Abstract: Combined with geological and production performance data in 4 sand group of upper Ng in Gudao Oilfield,the threedimensional
typical model reflecting reservoir architecture of point bar is set up according to quantitative description of lateral
accretion interbed in point bar. Based on economic limit production of horizontal well,the methods of reservoir engineering
and numerical simulation are used to analyze the adaptability limits of point bar potential tapping by horizontal well at high
water cut stage on the basis of distribution modes of remaining oil under different injection-production patterns in point bar. The
result shows that when the dip direction of interbed is consistent with water injection,and permeability of interbed is less than
12 mD,dip angle is lower than 7°vertical extension length / reservoir thickness more than 0.46 and horizontal spacing less than
60 m,it is time to prepare for tapping the potential of horizontal wells. When the dip direction of interbed is opposite to water
injection,and the adaptability limits become 30 mD,11°,0.33 and 90 m respectively,it is time to carry out potential tapping.
Such results provide a certain theoretical guidance for application of horizontal wells in point bar at high water cut stage.

Key words: high water-cut stage, point bar, horizontal well, adaptability limit